$22M
Building construction & site development
According to Precedent Developments' 2026 Canadian Construction Costing Guide [4], university
teaching buildings in Vancouver are estimated at approximately $750-$1,250 per square foot but
no info regarding Abbotsford. Hence this source provides a basis for preliminary planning and
the final cost will depend on the facility's size, design, and site requirements.
Source: Altus Group, 2026 Canadian Construction Costing Guide
(reference 4).
$17M
HPC / GPU / computing infrastructure
According to Exxact [6] Corporation (2025), NVIDIA H200 NVL GPUs cost over US$25,000 each, while an
eight GPU server can cost more than US$200,000. These figures demonstrate the significant investment
required to establish AI computing capabilities and support our proposed budget allocation.
Source: Exxact Corporation (2025)
(reference 6).
$16.85M
Land acquisition
For land acquisition, Group 8 proposes purchasing the property located at 28310 Huntingdon Road,
Abbotsford, BC V4X 1A3.
The property consists of two parcels totaling approximately 151.31 acres with the asking price of
$16.85 million CAD (This is more than double the size of current UFV Abbotsford campus). Located approximately a 15 minute drive from UFV, this land offers
more than enough space for the proposed AI research and innovation facility.
Source: Fraser Valley MLS listing.
$10M
Research laboratories & specialized equipment
The University of Toronto's Guide to Construction [5] distinguishes building construction
from equipment and other project expenses. This supports our approach of budgeting laboratory
equipment separately from construction costs.
Source: University of Toronto,
A Practical Guide to Addressing Construction & Renovation (2024)
(reference 5).
$3M
Sustainability, power & cooling
An eight GPU H200 server can draw approximately 5-7 kW, making substantial electricity and heat
management requirements for AI computing. This supports the need to budget for appropriate
electrical capacity and efficient cooling systems.
Source: Exxact Corporation (2025)
(reference 6).
$15M
Contingency reserve
Held back rather than allocated, and tied directly to the cost of modular systems. It
is drawn on for upgrades at a frequency of roughly 36 months, which is the practical
response to rapid hardware obsolescence on a project that will not open its doors
until 2030.
See risk R-03, rapid hardware obsolescence.